首页> 外文期刊>Expert Systems with Application >Extraction of decision alternatives in construction management projects:Application and adaptation of NSGA-Ⅱ and MOPSO
【24h】

Extraction of decision alternatives in construction management projects:Application and adaptation of NSGA-Ⅱ and MOPSO

机译:施工管理项目决策方案的提取:NSGA-Ⅱ和MOPSO的应用与适应

获取原文
获取原文并翻译 | 示例
           

摘要

The time-cost trade-off problem is a known bi-objective problem in the field of project management. Recently, a new parameter, the quality of the project has been added to previously considered time and cost parameters. The main specification of the time-cost trade-off problem is discretization of the decision space to limited and accountable decision variables. In this situation the efficiency of the traditional methods decrease and applying of the evolutionary algorithms is necessary. In this paper, two evolutionary algorithms that originally search the decision space in a continuous manner including: (1) multi-objective particle swarm optimization (MOPSO) and (2) nondominated sorting genetic algorithm (NSGA)-H, are considered as the optimization tools to solve two construction project management problems. These problems are both in discrete domain including two or tree objectives, separately. In this regard, some procedures has been suggested and then applied to adopt both algorithms capable in solving the problems in a discrete domain. Results show the advantages and effectiveness of the used procedures in reporting the optimal Pareto for the optimization problems. Moreover, the NSGA-II is more successful in determining optimal alternatives in both time-cost trade-off (TCTO) and time-cost-quality trade-off (TCQTO) problems than the MOPSO algorithm.
机译:时间成本的权衡问题是项目管理领域中已知的双目标问题。最近,一个新参数,即项目质量已添加到先前考虑的时间和成本参数中。时间成本权衡问题的主要规格是将决策空间离​​散化为有限且负责任的决策变量。在这种情况下,传统方法的效率会降低,因此有必要应用进化算法。在本文中,最初以连续方式搜索决策空间的两种进化算法包括:(1)多目标粒子群优化(MOPSO)和(2)非支配排序遗传算法(NSGA)-H,被视为优化方法。解决两个建设项目管理问题的工具。这些问题都是在离散域中,分别包括两个目标或树目标。在这方面,已经提出了一些程序,然后将其应用于采用两种能够解决离散域问题的算法。结果显示了所用程序在报告优化问题的最佳帕累托方面的优势和有效性。而且,与MOPSO算法相比,NSGA-II在确定时间成本权衡(TCTO)和时间成本质量权衡(TCQTO)问题中的最佳替代方案方面更为成功。

著录项

  • 来源
    《Expert Systems with Application》 |2012年第3期|p.2794-2803|共10页
  • 作者单位

    Department of Irrigation G' Reclamation Engineering, Faculty of Agricultural Engineering & Technology, College of Agriculture & Natural Resources, University of Tehran, Karaj, Tehran, Iran;

    Department of Irrigation G' Reclamation Engineering, Faculty of Agricultural Engineering & Technology, College of Agriculture & Natural Resources, University of Tehran, Karaj, Tehran, Iran;

    Department of Engineering, Shahrekord University, Shahrekord, Iran;

    Department of Land, Air & Water Resources, Department of Civil & Environmental Engineering, and Department of Biological & Agricultural Engineering, University of California,139 Veihmeyer Hail, University of California, Davis, CA 95616-8628, USA;

  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

    rroject management; time-cost-quality trade-off; NSCA-Ⅱ; MOPSO;

    机译:项目管理;时间-成本-质量的权衡;NSCA-Ⅱ;莫普索;