A comparison of the performance of various project control methods using earned value management systems

机译:使用挣值管理系统比较各种项目控制方法的性能

获取原文
获取原文并翻译 | 示例
           

摘要

Recent literature on project management has emphasised the effort which is spent by the management team during the project control process. Based on this effort, a functional distinction can be made between a top down and a bottom up project control approach. A top down control approach refers to the use of a project control system that generates project based performance metrics to give a general overview of the project performance. Actions are triggered based on these general performance metrics, which need further investigation to detect problems at the activity level. A bottom up project control system refers to a system in which detailed activity information needs to be available constantly during the project control process, which requires more effort. In this research, we propose two new project control approaches, which combines elements of both top down and bottom up control. To this end, we integrate the earned value management/earned schedule (EVM/ES) method with multiple control points inspired by critical chain/buffer management (CC/BM). We show how the EVM/ES control approach is complementary with the concept of buffers and how they can improve the project control process when cleverly combined. These combined top down approaches overcome some of the drawbacks of traditional EVM/ES mentioned in the literature, while minimally increasing the effort spent by the project manager. A large computational experiment is set up to test the approach against other control procedures within a broad range of simulated dynamic project progress situations.
机译:有关项目管理的最新文献强调了管理团队在项目控制过程中所付出的努力。基于此工作,可以在自上而下和自下而上的项目控制方法之间进行功能区分。自上而下的控制方法是指使用项目控制系统,该系统会生成基于项目的绩效指标,以对项目绩效进行总体概述。根据这些一般性能指标触发操作,需要进一步调查以在活动级别上发现问题。自下而上的项目控制系统是指在项目控制过程中需要不断提供详细的活动信息的系统,这需要更多的工作。在这项研究中,我们提出了两种新的项目控制方法,它们结合了自上而下和自下而上的控制元素。为此,我们将挣值管理/获利时间表(EVM / ES)方法与受关键链/缓冲区管理(CC / BM)启发的多个控制点集成在一起。我们展示了EVM / ES控制方法如何与缓冲区的概念互补,以及在巧妙地组合后如何改善项目控制过程。这些自上而下的组合方法克服了文献中提到的传统EVM / ES的某些缺点,同时最小化了项目经理的工作量。建立了一个大型计算实验,以在广泛的模拟动态项目进度情况下针对其他控制程序测试该方法。

著录项

  • 来源
    《Expert Systems with Application》 |2015年第6期|3159-3175|共17页
  • 作者

    Jeroen Colin; Mario Vanhoucke;

  • 作者单位

    Faculty of Economics and Business Administration, Ghent University, Tweekerkenstraat 2, 9000 Gent, Belgium;

    Faculty of Economics and Business Administration, Ghent University, Tweekerkenstraat 2, 9000 Gent, Belgium,Technology and Operations Management, Vlerick Business School, Keep 2, 9000 Gent, Belgium,Department of Management Science and Innovation, University College London, Gower Street, London WC1E 6BT, United Kingdom;

  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

    Project management; Schedule control; Earned value management (EVM); Simulation;