This article is based on AACE International Recommended Practice 57R-09 that defines the integrated analysis of schedule and cost risk to estimate the appropriate level of cost and schedule contingency reserve on projects. The main contribution of this RP is to include the impact of schedule risk on cost risk and the need to hold cost contingency reserves. Additional benefits include the application of the risk drivers method of using risks to drive the Monte Carlo simulation of a resource-loaded CPM schedule. By using the risks, one can prioritize the risks to cost, some of which are commonly thought of as risks to schedule, so that risk mitigation may be conducted in an effective way. The methods presented in the RP are based on integrating the cost estimate with the project schedule by resource-loading and costing the schedule's activities. Using Monte Carlo techniques one can simulate both time and cost simultaneously, permitting calculation of the impacts of schedule risk on cost risk. This article was presented as RISK.1043 at the 2012 AACE International Annual Meeting in San Antonio, Texas. It was ranked as the number three paper out of 99 presentations given and rated at the Annual Meeting.
机译:本文基于AACE国际推荐惯例57R-09,该惯例定义了进度和成本风险的综合分析,以估算项目的成本和进度应急准备金的适当水平。该计划的主要贡献是包括进度风险对成本风险的影响以及持有成本应急准备金的需要。其他好处包括应用风险驱动程序方法,该方法使用风险来驱动资源加载的CPM计划的蒙特卡洛模拟。通过使用风险,人们可以将风险优先于成本,其中一些风险通常被认为是计划风险,因此可以有效地进行风险缓解。 RP中提出的方法是基于通过资源加载和进度计划活动的成本将成本估算与项目进度表整合在一起的。使用蒙特卡洛技术,可以同时模拟时间和成本,从而可以计算进度风险对成本风险的影响。本文在德克萨斯州圣安东尼奥市2012年AACE国际年会上以RISK.1043的形式提出。在年度会议上发表和评价的99份报告中,它被列为第三名。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号