The Contemporaneous Period Analysis - Split Methodology Forensic Delay, MIP 3.4

机译:同时期分析-拆分方法取证延迟,MIP 3.4

获取原文
获取原文并翻译 | 示例
           

摘要

The Contemporaneous Period Analysis - Split methodology (Method ImplementationProtocol 3.4), is used when a schedule update has been performed based on progress,but schedule modifications have also been made before the schedule is published orsubmitted. When evaluating liability for delays (and damages related to acceleration)it is necessary to properly assign the project delay to the responsible critical workactivities, events, or schedule revisions. This methodology splits the analysis of delaysbetween progress and schedule revisions so each can be evaluated separately, andallows identification and monitoring of lessons learned from forensic analysis, such asre-planning failures and erosion of vital float through casual mitigation efforts. This articlewill discuss the steps in this process, provide examples of how the method works, anddiscuss the evaluation of the results. This article was first presented at the 2016 AACEInternational Annual Meeting as CDR.2620.
机译:如果根据进度执行了计划更新,则使用了“同时期分析-拆分”方法(方法实现 r nProtocol 3.4), r n但在计划发布或提交之前也进行了计划修改。 。在评估延误责任(以及与加速相关的损害)时,必须适当地将项目延误分配给负责的关键工作,活动,事件或时间表修订。这种方法将进度分析和进度修订之间的延迟分析分开,因此可以分别进行评估,并且 r n不能识别和监视从法医分析中学到的经验教训,例如 n n计划失败和重要因素的侵蚀通过不定期的缓解措施浮动。本文 r n将讨论该过程中的步骤,提供该方法如何工作的示例,并讨论结果的评估。本文最初在2016年AACE r n国际年会上以CDR.2620的形式发表。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号