Practical crack control during the construction of precast segmental box girder bridges

机译:预制分段箱梁桥施工中的实际裂缝控制

获取原文
获取原文并翻译 | 示例
           

摘要

Cracks that occurred in the bottom slab of a precast segmental bridge were investigated through a construction sequence analysis, which revealed that the cracks were caused by excessive deformation during temporary post-tension-ing while joining the segments. In addition, a parametric study was performed to evaluate the effects of the prestressing sequence, bottom slab thickness, and position of the prestressing anchors. The structural behavior of the girder sections was greatly affected by the thickness of the bottom slab and the position of prestressing anchors, but not by the prestressing sequence. Based on the results, a construction method that prevents the cracks is proposed.
机译:通过施工顺序分析研究了预制分段桥的底部平板中出现的裂缝,该裂缝表明,这些裂缝是由于在连接这些分段时的临时后张拉过程中过度变形引起的。此外,进行了参数研究,以评估预应力顺序,底板厚度和预应力锚杆位置的影响。大梁截面的结构行为受底板的厚度和预应力锚的位置的影响很大,但不受预应力顺序的影响。根据结果​​,提出了一种防止裂缝的施工方法。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号