首页> 外文期刊>Computers & Industrial Engineering >Resource constrained project scheduling problem with discounted earliness-tardiness penalties: Mathematical modeling and solving procedure
【24h】

Resource constrained project scheduling problem with discounted earliness-tardiness penalties: Mathematical modeling and solving procedure

机译:提前/迟到的折价罚金的资源受限项目调度问题:数学建模和求解过程

获取原文
获取原文并翻译 | 示例
           

摘要

In this paper, we consider the resource-constrained project scheduling problem with a due date for each activity. The objective is to minimize the net present value of the earliness-tardiness penalty costs. The problem is first mathematically modeled. Then, two meta-heuristics, genetic algorithm and simulated annealing are proposed to solve this strongly NP-hard problem. Design of experiments and response surface methodology are employed to fine-tune the meta-heuristics' parameters. Finally, a comprehensive computational experiment is described, performed on a set of instances and the results are analyzed and discussed.
机译:在本文中,我们考虑了每个活动的截止日期的资源受限项目计划问题。目的是最大程度地减少提前/迟到惩罚成本的净现值。首先对问题进行数学建模。然后,提出了两种元启发式算法,遗传算法和模拟退火算法来解决这一强NP难问题。实验设计和响应面方法被用来微调元启发法的参数。最后,描述了一个综合的计算实验,对一组实例进行了实验,并对结果进行了分析和讨论。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号