钢筋砼人工湖(池)施工的质量控制

         

摘要

针对以往钢筋混凝土水池施工所暴露的问题,福建林业职业技术学院江南新校区人工湖在夏季温度较高的施工条件下,通过采取一系列施工技术措施——处理好水池基底、严格控制混凝土温度、降低内外温差、处理好池体变形缝、施工缝等保证了工程的质量,抗渗试验效果良好.%In the artificial lake construction of Jiangnan new School of Fujian Forestry Vocational Technical College, it takes many construction measures which solve the problems of reinforced concrete pool construction in high temperature construction condition. Those technical measures include handling the pool base, controlling temperature of concrete strictly, reducing the difference of inside and outside temperature, handling deformation joints and construction cracks and so on, which guarantee the quality of the project and get a good effect in impermeability test.