根据腾龙桥二级水电站枢纽区工程地质勘察,通过对左岸滑坡勘察、计算、分析后认为,大坝位置布置在滑坡上游,并对滑坡进行处理,导流隧洞、厂房不宜布置在左岸.为工程布置、节约投资、工程安全建设提供可靠的地质建议.%According to engineering geological investigation of junction area of Tenglongqiao second cascade hydropower station,through the analysis,investigation and calculation of the left bank landslide.It is considered that the dam is located in the upper reaches of the landslide,and the landslide is processed.Diversion tunnel and buildings should not be arranged in the left bank.It provides reliable geological suggestion for engineering layout,saving investment and construction safety.