接驳缓冲设置中的独立时差策略

     

摘要

加入接驳缓冲后可能导致关键链与非关键链产生资源冲突,非关键链溢出等问题,使得关键链调度计划的制定再次复杂化. 为优化接驳缓冲的计算,在根方差法的基础上,运用独立时差这一项目网络提供的隐性安全时间,区分非关键链上的活动;并对非关键链上拥有独立时差的活动,改变Goldratt提出的所有非关键活动最晚执行策略,构建考虑独立时差的接驳缓冲设置方法. 通过仿真实验,对采用不同接驳缓冲设置法得到的关键链调度计划进行比较;结果表明,新方法能减少接驳缓冲设置引发的问题,并较好地改善了项目工期,项目执行绩效.%Inserting feeding buffer in non-critical chain may lead to new problems, such as new resource conflict, non-critical chain overflow, etc.These problems further complicate the resource constrained pro-ject scheduling.In order to optimize the sizing of feeding buffer, based on root square error method ( RSEM) , independent float is applied to solve the feeding buffer setting in critical chain project manage-ment theory.Using independent float wish is the hidden safety time in project network, the activities on non-critical chain are differentiated.Aiming at the non-critical activities which have independent float, and changing the latest time execution strategy proposed by Goldratt, the new feeding buffer sizing ap-proach is built.At the end, experimentation of different plans using various feeding buffer sizing methods has been done by means of simulation for contrastive analysis.Results show that the new approach reduces the problems caused by the feeding buffer inserting and improves the due date and execution performance of project.

著录项

相似文献

  • 中文文献
  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号