A Retrospective Quantitative Correlational Study of Logging Task Time and Completing Project Cycles

机译:记录任务时间和完成项目周期的追溯定量相关性研究

获取原文
获取原文并翻译 | 示例

摘要

Software development teams have difficulties meeting project schedules. Studies conducted in both 2008 and 2015 show over 68% of software projects failed or had trouble. Multiple studies have rated the Team Software Process (TSP) methodology to be a best practice that is beneficial in helping teams to deliver their work on schedule. A 2018 study reported that while most Naval Air Systems Command (NAVAIR) teams using TSP performed better than the industry average, some teams were still unable to meet their schedules. Multiple studies have reported that the lack of analytical support of TSP data is preventing teams from realizing the full benefits of the methodology. This study was conducted to determine if the consistency with which NAVAIR TSP teams log their task time (i.e., log task time in 'real time' or backfill the time-log later) has any relationship to the teams' ability to complete their projects on schedule and to generate coaching guidelines to direct teams to pursue best practices. This research used a retrospective quantitative correlational design to analyze project cycle data from NAVAIR teams using TSP from 2005--2017. The study analyzed the project cycle data by performing ANCOVA to remove the within-group variance of SPI from teams incorrectly estimating the task labor and incorrectly estimating the labor they can commit to the project (e.g., the number of task hours a week a team plans to log on the project). This research did not find a statistically significant correlation between time-log backfilling and completing a project cycle on schedule, but the study did quantify the importance of other TSP metrics (e.g., Cost Performance Indicator (CPI), Direct Time Ratio) as important factors that contribute to a team completing a project cycle on schedule. This study generated coaching guidelines to assess teams concerning issues with plans that have not yet fully impacted their ability to complete their project cycles on schedule.
机译:软件开发团队难以满足项目进度。 2008年和2015年进行的研究表明,超过68%的软件项目失败或遇到麻烦。多项研究已将团队软件流程(TSP)方法论评为最佳实践,这有助于帮助团队按时完成工作。一项2018年的研究报告说,尽管大多数使用TSP的海军航空系统司令部(NAVAIR)的表现都比行业平均水平要好,但一些团队仍无法按时完成计划。多项研究报告称,缺乏TSP数据的分析支持正在阻止团队实现该方法的全部优势。进行这项研究是为了确定NAVAIR TSP团队记录其任务时间(即“实时”记录任务时间或稍后回填时间日志)的一致性与团队完成其项目的能力是否相关。制定时间表并生成指导方针,以指导团队追求最佳实践。这项研究使用回顾性的定量相关设计,使用TSP从2005--2017年来分析来自NAVAIR团队的项目周期数据。该研究通过执行ANCOVA来消除团队的SPI的组内差异,从而分析了项目周期数据,这些团队不正确地估计了任务的工作量,并且错误地估计了他们可以承担的项目工作量(例如,团队每周计划的工作小时数登录该项目)。这项研究并未发现时间日志回填与按计划完成项目周期之间的统计显着相关性,但该研究确实量化了其他TSP指标(例如成本绩效指标(CPI),直接时间比例)的重要性有助于团队按时完成项目周期。这项研究生成了指导方针,以评估与计划问题有关的团队,这些问题尚未完全影响其按计划完成项目周期的能力。

著录项

  • 作者

    Hodgins, Bradley.;

  • 作者单位

    Colorado Technical University.;

  • 授予单位 Colorado Technical University.;
  • 学科 Computer science.;Computer engineering.
  • 学位 D.C.S.
  • 年度 2018
  • 页码 125 p.
  • 总页数 125
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号