Empirically based risk factors for software intensive weapon system programs.

机译:软件密集型武器系统程序的基于经验的风险因素。

获取原文
获取原文并翻译 | 示例

摘要

Seventy-two software intensive weapon systems programs were researched from reports that spanned over a six-year period. Of these fifty-two were deemed software intensive systems and of those thirty-nine developed significant cost, schedule or performance issues either during development or shortly after deployment. A list of seven separately published risk indicators based on industry experience from these kinds of systems was combined, scored and quantified to produce an overall ranking of areas to assess with a questionnaire. A 218-question questionnaire was developed and used to assess a major Software Intensive Weapon System Program. This questionnaire, developed from the integrated risk list, utilized a six-item Likert scale (including N/A) to help quantify specific areas of risk. The questionnaire was organized to facilitate the assessment and a video was developed to explain the purpose of the research and to help with taking the questionnaire. Results from the assessment were used to develop the leading risk indicators - both the highly positive and highly negative scored questions were used to identify areas of strength and weakness of the Assessed Program to develop a comprehensive set of questions organized around eleven Key Areas and twenty-nine Supporting Practices - the Empirical Risk Factors Assessment table. An approach is developed based on the application of these risk areas to Software Intensive Weapon System Programs to lessen the impact of shortened schedules and reduced budgets that are hallmarks for these kinds of efforts. Detailed observations are made in terms of strengths and weaknesses of the Assessed Program that provide deep insights into issues dealt with and possible mitigations.;The empirically based risk factors were assessed by two independent experts who worked for the DoD and were responsible for many Software Intensive Weapon System Program acquisition efforts. Indications from both were that these were very effective risk measures and helped to highlight specific areas of risk for these kinds of programs.
机译:根据长达六年的报告,研究了72个软件密集型武器系统程序。在这五十二个被认为是软件密集型系统中,在这三十九个中,无论是在开发期间还是在部署后不久,都出现了重大的成本,进度或性能问题。基于来自这些类型系统的行业经验,对七个单独发布的风险指标进行了列表,评分和量化,以得出要调查的领域的总体排名。开发了218个问题的问卷,并用于评估主要的软件密集武器系统计划。该问卷是从综合风险列表中开发出来的,采用了六项李克特量表(包括N / A)来帮助量化特定风险领域。组织了调查问卷以促进评估,并制作了一段视频以解释研究目的并帮助您完成调查问卷。评估结果被用来制定主要的风险指标-高度积极和高度消极的得分问题都被用来确定评估计划的优缺点,从而围绕11个关键领域和20个关键领域组织了一套全面的问题九种支持实践-经验风险因素评估表。基于将这些风险领域应用于软件密集型武器系统程序,开发了一种方法,以减轻缩短计划表和减少预算的影响,而这是此类工作的标志。根据评估程序的优缺点进行了详细的观察,从而对处理的问题和可能的缓解措施提供了深刻的见解。基于经验的风险因素是由两位独立的专家评估的,这些专家为国防部工作,并负责许多软件密集型武器系统计划的获取工作。两者均表明这是非常有效的风险衡量标准,有助于突显此类计划的特定风险领域。

著录项

  • 作者

    Robb, John H.;

  • 作者单位

    Southern Methodist University.;

  • 授予单位 Southern Methodist University.;
  • 学科 Computer science.
  • 学位 D.E.
  • 年度 2014
  • 页码 274 p.
  • 总页数 274
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号