NOT YOUR AVERAGE WALLPAPER –REHABILITATION OF THE WOOD STREET INTERCEPTOR

机译:不是您的平均墙纸-伍德街拦截器的修复

获取原文
获取原文并翻译 | 示例

摘要

The Wood Street Interceptor project involved the rehabilitation of 3,000 feet of 105-rninch diameter reinforced concrete sewer pipeline that was 50 years old and graduallyrndeteriorating due to hydrogen sulfide corrosion. East Bay Municipal Utility Districtrn(District) has completed two rehabilitation projects in the Wood Street Interceptorrnusing the Danby and Linabond processes to install corrosion resistant PVC liners. Byrninstalling corrosion resistant liners, the useful life of the pipeline has been extendedrnby another 50 to 100 years.rnThe Danby rehabilitation method involves installing PVC forms over the pipe interiorrnsurface and placing cementitous grout behind the forms in several lifts over severalrndays.rnThe Linabond rehabilitation method involves spraying of a high strengthrnthermosetting resin to the surface of the concrete pipe. The resin expands in anrnexothermic reaction to form a section of rigid cellular plastic which firmly bonds withrnthe concrete. A thin flexible PVC liner was then placed over the resin.rnThe construction effort was remarkable for its efficiency and high level ofrncoordination under hazardous confined space conditions. Because the interceptorrnremained active, work had to be performed during a 6-hour window at night whenrnflows were at their lowest. Rigorous safety measures were required to ensure thernsafety of personnel in the pipeline. Close coordination was required with operationsrnstaff at the downstream treatment plant influent pump station to ensure thatrninterceptor levels were maintained low enough for work to occur. As a result of thernexcellent coordination effort, the project was completed with an excellent safetyrnrecord, no lost construction days and no community complaints and zero changernorder.
机译:伍德街拦截器项目涉及3,000英尺长,直径105英寸的钢筋混凝土下水管道的修复,该管道已有50年的历史,并由于硫化氢腐蚀而逐渐恶化。东湾市政公用事业区(区)已通过使用Danby和Linabond工艺安装耐腐蚀PVC衬里,在伍德街拦截器中完成了两个修复项目。通过安装耐腐蚀衬里,管道的使用寿命又延长了50到100年.Danby修复方法包括将PVC模板安装在管道内表面上,并在模板中将水泥浆灌入模型中数天后的数次提升中。在混凝土管表面喷涂高强度的热固性树脂。树脂在放热反应中膨胀,形成一块刚性的多孔塑料,与混凝土牢固粘结。然后将薄的柔性PVC衬里放在树脂上。由于在危险的密闭空间条件下其效率高和协调性高,因此在施工方面的工作非常出色。由于拦截器仍处于活动状态,因此必须在夜间流量最低的6小时内进行工作。需要采取严格的安全措施以确保管道中人员的安全。下游处理厂进水泵站的操作人员需要密切配合,以确保拦截器的水平保持在足够低的水平以进行工作。由于出色的协调工作,该项目以出色的安全记录,无损失的施工天数,无社区投诉和零变更的顺序完成。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号