Repair or Replace-What to do with a 20-Year Old Scrubber: East Kentucky Power Cooperative's Spurlock Unit 2 WFGD Retrofit

机译:修理或更换 - 与20岁的洗涤器有关:East Kentucky Power Cooperative的Spurlock Unit 2 WFGD改装

获取原文

摘要

East Kentucky Power Cooperative's (EKPC) Spurlock Unit 2 (525 MW) is presently equipped with a lime-based, wet flue gas desulfurization (WFGD) system that was initially placed into service in the early 1980's. The Unit 2 WFGD system was decommissioned shortly after start-up when it was determined that environmental compliance could be achieved more economically by fuel switching. Recently, EKPC decided to reduce SO{sub}2 emissions from Spurlock Unit 2. EKPC conducted an extensive evaluation of options that included: Refurbishment of the existing system, Converting the existing system to forced-oxidation limestone/gypsum operation, and Replacing the existing WFGD system with a state-of-the-art forced-oxidation limestone system. The following paper summarizes the economic evaluation and decisions that led to the decision to replace the existing WFGD system with a new, single absorber limestone-based system utilizing ALSTOM's open spray tower technology. Key design features of the new WFGD system are also discussed.
机译:East Kentucky Power Cooperative(EKPC)Spurlock Unit 2(525 MW)目前配备了基于石灰的湿法烟气脱硫(WFGD)系统,最初在20世纪80年代初期置于服务中。当确定通过燃料切换可以更经济地实现环境规则时,初始在启动后不久会退出单元2 WFGD系统。最近,EKPC决定减少Spurlock Unit的{Sub} 2排放2. EKPC对包括:翻新现有系统的选择进行了广泛的评估,将现有系统转化为强制氧化石灰石/石膏操作,并更换现有系统WFGD系统具有最先进的强制氧化石灰岩系统。以下论文总结了导致替代现有WFGD系统的经济评估和决定,利用AlstoM开放的喷雾塔技术用新的单吸收式石灰石的系统取代现有的WFGD系统。还讨论了新WFGD系统的关键设计特征。

著录项

相似文献

  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号