Application of the Time 'at large' Principle to Standard Forms of Contract

机译:时间“一般”原则在标准合同形式中的应用

获取原文

摘要

The contractor has an obligation to complete the works within the time for completion, and the employer should not impede the contractor in performing its obligations under the contract. To this end, if the contractor is prevented from completing by the date for completion by an act of prevention by the employer and there is no corresponding right to extend time for completion as a result of such act, or the time for completion is not properly extended, time becomes 'at large'. Accordingly, the contractor is not under the obligation to complete the works within the original time for completion and he should complete within a reasonable time. This paper used a two-step research methodology where the time 'at large' principle is explained within the context of the common law legal system and is consequently applied to various standard forms of contract. The standard forms of contract examined in this paper include the Joint Contracts Tribunal (JCT) Design and Build Contract of 2011, the World Bank Conditions of Contract (WB Contract) included in the Standard Bidding Documents for Procurement of Works (SBDW), the Federation of Consulting Engineers (FIDIC) Conditions of Contract for Construction issued in 1999, and the American Institute of Architects (AIA) Conditions of contract for Construction (A201) of 2007. The authors highlighted the provisions related to delays and extension of time and mapped to them the principle of time 'at large' to conclude when time could become 'at large' under the subject contracts. This study helps employers and contractors - entering into projects using any of these standard forms of contract within a common law legal system - to avoid conflicts, claims, and disputes associated with and/or resulting from the time 'at large' principle. This should support effective and efficient contract administration of construction projects.
机译:承包商有义务在完成时完成工作,雇主不应阻止承包商在合同下履行其义务。为此,如果承包商被雇主预防行法预防完成的日期,并且由于此类法案而没有相应的权利延期完成时间,或者完成时间不正确延伸,时间变得“大”。因此,承包商不属于在原始时间内完成工作的义务,并且他应该在合理的时间内完成。本文使用了两步的研究方法,其中在普通法法律制度的背景下解释了“大的”原则“的时间”,因此应用于各种标准形式的合同。本文审查的标准合同形式包括2011年的联合合同法庭(JCT)设计和建立合同,纳入贸易署(SBDW),联邦的标准招标文件中纳入的世界银行条件(WB合同)咨询工程师(FIDIC)1999年颁发的建设合同条件,以及美国建筑师协会(AIA)建设合同条件(A201),2007年突出了与延迟和延长时间相关的规定,并映射到他们在受试者合约下的时间“大会”时,他们的时间“很大”的原则。本研究有助于雇主和承包商 - 利用普通法法律制度中的任何标准形式的合同进入项目 - 以避免与之相关的冲突,索赔和争议,以较大的原则。这应支持建筑项目的有效和高效的合同管理。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号