V The Missouri Department of Transportation is completing the Route 249 - US 171 interchange on an abandoned underground lead-zinc mining site near Joplin, Missouri. The interchange required the construction of 5 major bridges connecting massive earth embankments and involved the construction of 23 bents, 3 culverts and 3 MSE walls. The geotechnical characteristics of the project site are the product of the original limestone and chert bedrock geology, the tectonic processes leading to brecciation, folding and paleo karst, and the anthropogenic (manmade) activities associated with mining. These processes resulted in a site that exhibited critical geotechnical attributes: 1. Highly variable rock parameters (strength, deformability and hydraulic conductivity) 2. Very low level of predictability or correlation between subsurface explorations 3. Locally modified hydrologic regime due to the mining disturbance 4. Presence of residual mining voids in both the upper "confused" zone and the lower "sheet" zone 5. Potential for ground loss beneath foundation elements 6. Presence of heterogeneous mine fillings including compressible clay 7. Presence of vertical shafts with random and partial filling These attributes led the design team to the selection of a foundation design concept that required bent specific geologic characterization based on subsurface exploration and geotechnical testing; pre design utilizing stress analyses and other analytical approaches to predict the interaction of ground quality, voids and imposed loading; systematic confirmatory exploration during construction; and ground treatment and foundation design modifications as required by the confirmatory construction site engineering and inspection work. The basic premise of this approach was that there were no foreseeable ground conditions at the project site that could not be adequately improved to provide foundation support for the proposed structures. Discussions during the pre bid phase emphasized ground conditions would be evaluated on a continuous basis in the field, reducing or eliminating any delays. This paper describes the historical research, site investigation, design methodologies and construction of spread footings at 7 of the bents and the 220 micropiles used to provide deep foundations for 16 of the bents. Pregrouting of the rock mass involved 8698 yds~3 (6,650 m~3) of LMG and 504 yds~3 (385 m~3 ) HMG and was conducted to confirm design assumptions at all bents and as a site preparation for those bents to, be micropiled. A separate program of mine shaft location and treatment was also required.
机译:五,密苏里州交通运输部正在密苏里州乔普林附近一个废弃的地下铅锌矿场完成249号公路-美国171号公路的换乘。交汇处需要建造5座连接大型土堤的主要桥梁,涉及建造23个弯头,3个涵洞和3个MSE墙。该项目场地的岩土工程特征是原始石灰岩和石基岩地质,导致断裂,褶皱和古岩溶的构造过程以及与采矿相关的人为(人造)活动的产物。这些过程导致了一个具有关键岩土属性的场地:1.高度可变的岩石参数(强度,变形性和水力传导率)2.地下勘探的可预测性或相关性水平非常低3.由于采矿干扰而局部修改了水文状况4 。上部“混乱”区域和下部“薄板”区域均存在残留的采矿空洞5.地基元素下方的地面流失的可能性6.存在包括可压缩粘土在内的非均质矿山填充物7.存在带有随机和部分竖井的竖井填充这些属性使设计团队选择了一个基础设计概念,该概念要求根据地下勘探和岩土工程测试对特定的地质特征进行弯曲;利用应力分析和其他分析方法进行预设计,以预测地面质量,空隙和施加的载荷之间的相互作用;施工期间进行系统的确认性探索;并按照验证性建筑工地工程和检查工作的要求进行地面处理和基础设计修改。这种方法的基本前提是,项目现场没有可预见的地面条件,无法对其进行充分改善以为拟议结构提供基础支持。预投标阶段的讨论着重于地面条件,将在现场进行连续评估,以减少或消除任何延误。本文介绍了7个折弯的历史研究,现场调查,设计方法和摊铺基础的构造以及220个微型桩,这些桩为16个折弯提供了深厚的基础。岩体的预灌浆涉及LMG的8698 yds〜3(6,650 m〜3)和HMG的504 yds〜3(385 m〜3)HMG,并进行了确认以确认所有弯头的设计假设,并为这些弯头的现场准备工作,被微型化。还需要一个单独的矿井定位和处理程序。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号