REMODELING METHOD OF SHEET PILE TYPE QUAY

机译:板桩码头改造方法

摘要

PROBLEM TO BE SOLVED: To remove a tie rod and conduct remodeling construction works in the remodeling construction works of a sheet pile type quaywall under the state, in which a sheet-pile wall and brace works are connected by the tie rod. ;SOLUTION: A caisson body 5 is moved on water and arranged in front of the sheet pile type quaywall. Piles 8 are driven to the bottom of water from the caisson body 5 while water is poured into the caisson body 5 and the caisson body 5 is sunk. The sheet-like wall 2 of the sheet pile type quaywall is pushed backwards by hydraulic jacks 7 installed onto the side face of the caisson body 5, and the existing steel-pipe sheet piles 4 of the sheet-pile wall 2 are supported. Accordingly, since the existing steel-pipe sheet piles 4 are brought to the state, in which they are supported by the caisson body 5, tie rods 3 bearing the existing steel-pipe sheet piles 4 can be removed. A ground at the rear of the existing steel-pipe sheet piles 4 is improved under the state, in which the tie rods 3 are taken off, but soil can be improved easily and surely because there is no tie rod 3 at that time.;COPYRIGHT: (C)1999,JPO
机译:解决的问题:在通过拉杆将板桩墙和支杆工程连接起来的状态下的板桩式码头的改建工程中,拆除拉杆并进行改建工程。 ;解决方案:沉箱主体5在水上移动,并布置在板桩式码头的前面。当将水倒入沉箱主体5中并且沉箱主体5沉没时,将桩8从沉箱主体5打入水底。板桩式码头墙的板状壁2被安装在沉箱主体5的侧面上的液压千斤顶7向后推,支撑板桩壁2的现有的钢管板桩4。因此,由于将现有的钢管板桩4设为由沉箱主体5支撑的状态,因此能够卸下支承有现有的钢管板桩4的拉杆3。在拉下拉杆3的状态下,改善了现有钢管板桩4的后方的地面,但是由于当时没有拉杆3,因此能够容易且确实地改善土壤。版权:(C)1999,日本特许厅

著录项

  • 公开/公告号JPH11323872A

    专利类型

  • 公开/公告日1999-11-26

    原文格式PDF

  • 申请/专利权人 TOYO CONSTR CO LTD;

    申请/专利号JP19980132200

  • 发明设计人 YASUOKA KEIICHI;OMAE MASATSUGU;

    申请日1998-05-14

  • 分类号E02B3/06;

  • 国家 JP

  • 入库时间 2022-08-22 02:03:02