Four payment models for the multi-mode resource constrained project scheduling problem with discounted cash flows

机译:现金流打折的多模式资源受限项目调度问题的四种支付模型

摘要

In this paper, the multi-mode resource constrained project scheduling problem with discounted cash flows is considered. The objective is the maximization of the net present value of all cash flows. Time value of money is taken into consideration, and cash in- and outflows are associated with activities and/or events. The resources can be of renewable, nonrenewable, and doubly constrained resource types. Four payment models are considered: Lump sum payment at the terminal event, payments at prespecified event nodes, payments at prespecified time points and progress payments. For finding solutions to problems proposed, audgenetic algorithm (GA) approach is employed, which uses a special crossover operator that can exploit the multi-component nature of the problem. The models are investigated at the hand of an example problem. Sensitivity analyses are performed over the mark up and the discount rate. A set of 93 problems from literature are solved under the four different payment models and resource type combinations with the GA approach employed resulting in satisfactory computation times. The GA approach is compared with a domain specific heuristic for the lump sum payment case with renewable resources and is shown to outperform it.
机译:本文考虑了现金流量折现的多模式资源受限项目调度问题。目标是使所有现金流量的净现值最大化。考虑到金钱的时间价值,现金流入和流出与活动和/或事件相关。这些资源可以是可再生,不可再生以及受双重约束的资源类型。考虑了四种付款模式:终端事件的一次性付款,预定事件节点的一次性付款,预定时间点的付款和进度付款。为了找到提出的问题的解决方案,采用了预算算法(GA)方法,该方法使用了一种特殊的交叉算子,可以利用问题的多分量性质。这些模型是通过示例问题进行研究的。对加价幅度和折现率进行敏感性分析。在四种不同的支付模型和资源类型组合下,采用GA方法解决了文献中的93个问题,从而获得了令人满意的计算时间。将GA方法与针对具有可再生资源的一次性付款案例的特定领域启发式方法进行比较,并证明其性能优于后者。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号