A case history of tunnelling through difficult ground

机译:穿越困难地面的案例

获取原文
获取原文并翻译 | 示例
           

摘要

Udhampur-Katra section is the first leg of the prestigious and challenging Udhampur-Srinagar-Baramulla Rail Link project covering a total length of 287.0 km in Jammu & Kashmir state of India. The project envisages construction of a new single line broad gauge railway with maximum speed potential of 100 km/h with ruling gradient limited to 1 in 100. The Udhampur-Katra section of the project is 25 km long, and it involves construction of 8 tunnels, aggregating to a total length of 10 km. Out of 8 tunnels, 2 tunnels - Tunnel No. 1 (3.2 km) and Tunnel No. 3 (2.5 km) - are over 2 km long. The Tunnel No. 1 is D-shaped with excavation width of 6.5 m and excavated height approximately 8.2 m. Generally the primary supports are steel ribs ISHB 150 with varying spacing depending up on the rock type. At some places double rings of steel ribs are also used.
机译:Udhampur-Katra路段是久负盛名的Udhampur-Srinagar-Baramulla铁路连接项目的第一站,该工程全长287.0公里,位于印度查mu和克什米尔邦。该项目计划建设一条新的单线宽轨铁路,最大时速潜力为100 km / h,统治坡度限制为100分之一。该项目的Udhampur-Katra段长25 km,涉及8条隧道的建设。 ,总长度为10公里。在8条隧道中,有2条隧道长1公里(3.2公里),而3号隧道长(2.5公里),长2公里。 1号隧道为D形,开挖宽度为6.5 m,开挖高度约为8.2 m。通常,主要支撑物是ISHB 150钢肋,其间距根据岩石类型而有所不同。在某些地方,也使用双环钢肋。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号