首页> 外文期刊>Processes >Deformation and Control Countermeasure of Surrounding Rocks for Water-Dripping Roadway Below a Contiguous Seam Goaf
【24h】

Deformation and Control Countermeasure of Surrounding Rocks for Water-Dripping Roadway Below a Contiguous Seam Goaf

机译:煤层采空区下泄水巷道围岩变形与控制对策

获取原文
           

摘要

To solve the technical problem of supporting a water-dripping roadway below contiguous seams at the Tuanbai coal mine, the deformation law of surrounding rocks for the roadway was studied using Fast Lagrangian Analysis of Continua in Three Dimensions (FLAC3D) numerical simulation. Then, a mechanical model of water-dripping rock using a bolt support was established, and further, technical countermeasures to control the deformation of the roadway with a bolt and cable support are proposed. The results show that the erosion of the water dripping on the roadway was substantial and showed notable changes over time during roadway excavation and mining work. These effects caused the road to heave slightly, but it tended to be stable during roadway excavation. Moreover, the erosion of the roof and two ribs increased exponentially, and the floor heave increased with significant displacement oscillation during mining. The anchoring length of bolts and the rock weakening from water dripping had noticeable effects on the surrounding rocks of the roadway. The logical parameters of the bolt spacing and tightening force (the bolt line spacing was 0.7–0.9 m and the tightening force exceeded 40 kN) of the bolt supports were studied and optimized. Finally, a support scheme for water dripping on the roadway at the Tuanbai coal mine is proposed. The observation data regarding the deformation of the surrounding rocks, monitoring of bolt and cable stress, endoscopy results of roof failure, and roof bed separation monitoring were used to verify the reasonableness of the scheme and ensure the requirements for support were met. The study results can serve as a reference regarding the support for water dripping on a roadway under similar conditions.
机译:为解决团白煤矿连续煤层下注水巷道支护的技术难题,采用三维连续体快速拉格朗日分析法(FLAC3D),研究了巷道围岩的变形规律。然后,建立了采用锚杆支护的滴水岩体力学模型,并提出了采用锚杆支护的控制巷道变形的技术对策。结果表明,在巷道开挖和采矿工作中,滴落在巷道上的水的侵蚀是严重的,并且随时间变化显着。这些影响使道路略有起伏,但在巷道开挖过程中趋于稳定。此外,顶板和两个肋骨的侵蚀呈指数增加,并且在开采过程中随着显着的位移振荡,底鼓增大。锚杆的锚固长度和因滴水而变弱的岩石对巷道周围的岩石有明显的影响。研究并优化了螺栓支架的螺栓间距和拧紧力(螺栓线间距为0.7-0.9 m,并且拧紧力超过40 kN)的逻辑参数。最后,提出了团白煤矿巷道水滴的支护方案。利用围岩变形,锚索应力监测,顶板破坏的内窥镜检查结果,顶板分离监测等观测资料,验证了方案的合理性,并保证了支护的要求。研究结果可为相似条件下巷道滴水支护提供参考。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号