RISK ANALYSIS IN CONSTRUCTION NETWORKS USING A MODIFIED STOCHASTIC ASSIGNMENT MODEL

机译:修正随机分配模型的建筑网络风险分析

获取原文
获取原文并翻译 | 示例
           

摘要

A review of construction network analysis indicates that new methods are needed for quantifying risks in project evaluation. The paper proposes a new analytical method, the Modified Stochastic Assignment Model (MSAM), for the prediction of project duration. The proposed method is inspired by a previous method used solely in traffic networks, the Stochastic Assignment Model (SAM). The MSAM method applies Clark's approximation to find the longest project duration. Two cases are used to demonstrate the validity and application of the MSAM in construction project evaluations. The accuracy of the MSAM is assessed by comparing it with the Monte Carlo Simulation (MCS). A comparison of the MSAM with other methods, such as PERT and PNET, has also been presented. It is found that the new method is an analytical counterpart of the MCS and is very efficient in saving computational time whilst taking full account of the correlations between paths.
机译:对施工网络分析的回顾表明,需要新的方法来量化项目评估中的风险。本文提出了一种新的分析方法,即改进的随机分配模型(MSAM),用于预测项目工期。所提出的方法是受之前仅用于交通网络的方法(随机分配模型(SAM))的启发。 MSAM方法应用Clark近似法来找到最长的项目工期。通过两个案例来证明MSAM在建设项目评估中的有效性和应用。通过将MSAM的准确性与蒙特卡洛模拟(MCS)进行比较来评估其准确性。还介绍了MSAM与其他方法(如PERT和PNET)的比较。发现该新方法是MCS的分析对等方,并且在节省计算时间的同时非常有效,同时充分考虑了路径之间的相关性。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号